Implementation Overview for ICT Service Providers

Implementation followed the principle: What causes immediate harm if not addressed?

Q1 2025        Q2 2025        Q3 2025        Q4 2025        2026           2027
────┬──────────┬──────────────┬──────────────┬──────────────┬──────────────┬────►
    │          │              │              │              │              │
    │  ┌───────┴──────┐      │              │              │              │
    │  │ P2: Incident │      │              │              │              │
    │  │ reporting    │      │              │              │              │
    │  │ process set  │      │              │              │              │
    │  │ up           │      │              │              │              │
    │  └──────────────┘      │              │              │              │
    │          │              │              │              │              │
    │  ┌───────┴──────────────┴──────┐      │              │              │
    │  │ P4: Contracts adjusted,     │      │              │              │
    │  │ information register data   │      │              │              │
    │  │ provided (client deadline:  │      │              │              │
    │  │ 30.04.2025)                 │      │              │              │
    │  └─────────────────────────────┘      │              │              │
    │                         │              │              │              │
    │                 ┌───────┴──────────────┴──────┐      │              │
    │                 │ P1: ICT risk management      │      │              │
    │                 │ framework formalised,         │      │              │
    │                 │ asset inventory, policies     │      │              │
    │                 └────────────────────────────────┘    │              │
    │                                        │              │              │
    │                                ┌───────┴──────────────┴──────┐      │
    │                                │ P3: Test programme           │      │
    │                                │ established, automation      │      │
    │                                │ rolled out                   │      │
    │                                └─────────────────────────────┘      │
    │                                                       │              │
    │                                               ┌───────┴──────┐      │
    │                                               │ P5: Threat   │      │
    │                                               │ intelligence │      │
    │                                               │ integrated   │      │
    │                                               └──────────────┘      │
    │                                                              ┌──────┴──┐
    │                                                              │FinmadiG │
    │                                                              │Extension│
    │                                                              └─────────┘

Phase 1: Immediate Actions (Q1 2025) ✅

P2: Incident Reporting

MeasureDeliverableStatus
Incident classification system introducedDecision tree (7 criteria)✅ Implemented
Pre-filled XML reporting template createdTemplate with static data✅ Implemented
Internal reporting deadline defined (< 1h to clients)SLA document✅ Implemented
Escalation chain documentedEscalation matrix✅ Implemented
SIEM alerting configured to DORA thresholdsMonitoring rules✅ Implemented

P4: Contractual Foundations

MeasureDeliverableStatus
DORA contract clauses template createdTerms supplement / contract annex✅ Implemented
DORA fact sheet for clients createdStandardised information sheet✅ Implemented
Subcontracting register set upCRM Custom Object✅ Implemented
Audit rights included in all contractsContractual clause✅ Implemented

Phase 2: Contract Adjustment (Q2 2025) ✅

P4: Register & Contracts

MeasureDeliverableCompleted
All financial sector clients identifiedClient listApril 2025
Affected contracts inventoriedContract list + gap analysisApril 2025
DORA info sheet provided to clientsFact sheetApril 2025
Contract adjustments negotiatedNew contracts / amendmentsJune 2025
Exit strategy template createdStandard documentMay 2025

Phase 3: Operational Implementation (Q3–Q4 2025) ✅

P1: ICT Risk Management

MeasureDeliverableCompleted
ICT risk management framework documentedPolicy documentJuly 2025
ICT asset inventory completedCMDB fully populatedAug 2025
Criticality classification conductedAsset classificationAug 2025
ICT security policy per RTS 2024/1774Policy updateSep 2025
BCP/DRP formalised with RPO/RTOBCP + DRP documentsSep 2025
Awareness programme set upLMS course + materialsOct 2025
Communication plan createdCommunication strategyOct 2025
Annual review process definedCalendar entries + process descriptionNov 2025

P3: Test Programme

MeasureDeliverableCompleted
Test programme policy createdTest programme documentAug 2025
Vulnerability scanning automatedVulnerability Scanner pipelineAug 2025
SAST integrated into CI/CDSAST-PipelineSep 2025
Annual pentest commissionedExternal providerQ4 2025
BCP/DRP test conductedTest protocolQ4 2025
Performance baseline establishedk6 benchmarksQ4 2025

Phase 4: Ongoing Operations (from 2026) ✅

CadenceMeasureResponsible
DailyDependency scanning (CI/CD)Automated
WeeklyVulnerability scan (infrastructure)Automated
MonthlyCompliance status reportAutomated + review
QuarterlyNetwork assessment, performance testAutomated
Semi-annuallyContract register reviewCompliance
AnnuallyPentest (external), BCP/DRP test, awareness trainingManagement
AnnuallyICT risk management framework reviewManagement
AnnuallyUpdate information register data + inform clientsCompliance
Every 3 yearsTLPT cooperation (upon client request)External

Ongoing Effort (annually)

ItemEffort (person-days/year)
Annual framework review2
Contract register maintenance2
Awareness training1
BCP/DRP test2
Pentest support2
Compliance reporting1
Total ongoing~10 person-days/year

Effort Reduction Through Automation

Without automation: ~25 person-days/year ongoing. With automation: ~10 person-days/year. Difference: ~15 person-days/year.